Case study #4 Private school

Case study #4 Private school
June 24, 2020 Ian Sterne

Located in an urban transitional zone, this school faced stray gunfire from neighboring buildings.

As a high-end private school for special needs children, administrators looked into conventional bullet proof glass. Cost estimates ranged in excess of $2M and required months of scheduled construction time.

ACE undertook the project for $320,000 with the work scheduled just after the Christmas break in 2016 to minimize impact on students. Work was completed in 12 days.

Total cost with ACE: $320,000
Savings compared to ballistic glass:  + $2M
Stock image.  Image is NOT of actual client site.